The Municipal District of Lesser Slave River completed the final stage of a $21.3 million wastewater facility in 2006 that provides rural sewage collection and treatment services to the Southshore communities of Canyon Creek, Widewater, Wagner, and Nine Mile Point.

The Southshore Sewer Project, which was the largest project ever undertaken by the municipality, was also Alberta’s first municipal membrane bioreactor and precedent setting in its use of new, innovative biotechnology.

Construction of a low pressure wastewater collection system, treatment facility, and wetland commenced in 2004 and was completed in late 2005. Since start-up in early 2006, the state-of-the-art facility has consistently produced high-quality effluent in terms of low organics, suspended solids, nutrients, and microorganisms, which will meet the demands of the community for the foreseeable future while protecting the environment.

Late 2011 saw the installation of a lift station, collector lines, and private service connections to over 250 residences. An additional 150 private service connections are scheduled for completion in 2012. All serviceable residents were required to connect to this municipal wastewater system per Bylaw 2003-08.

This successful project was the result of collaborative efforts of the municipality, Alberta Environment, Alberta Infrastructure and Transportation, Infrastructure Canada-Alberta Program, and area residents.